Construction Update

on September 15, 2016

Submitted by Jon Bechtel  

The concrete project has been slowed by rain but is moving forward. The driveway to the Park entrance is open from the West side parking lot. We will be finishing half of the resident reserved parking and carport (weather permitting) this week. While it is curing, we will start demolition of the concrete in front of Honstead up to the Lyle entrance. This area will be closed to all traffic during this time.

Upon completion of the third section we will go to the fourth section which is the south end Reserved resident parking and carport. The fifth section then be the north end between the Lyle entrance and where the asphalt starts. We are working to get this completed as soon as possible. Thank you for your patience.